Dirio Gas & Power Ltd

Dirio Ready To Supply Electricity

Directors of Dirio and PNG Power signed an agreement on Wednesday on 20th of October, which paves the way for Dirio to supply power into the Port Moresby PNG Power grid.

Dirio built and commissioned a 45 mega-watt (MW) power plant at Caution Bay in Central province in November 2020, but was unable to supply electricity due to PNG Power not building a transmission line nor having sufficient capacity and stability on the existing transmission line to take the full supply as per the Power Purchase Agreement.