K16 million for final phase of cancer facility construction

Chief Executive Officer for PMGH Dr Paki Molumi says this represents 35 percent of the contract value of more than K47 million and marks the start of the final phase of the project.

The cancer facility project was allocated K50 million by the national government in the 2022 budget.

This phase of the project will include what Dr Molumi says is a total feed out of works like plumbing, electrical and engineering services, air condition installation and radiation safety.